Monday, June 8, 2020

Turkey Creek Ph 1- Flat Creek (Line Work)


7:00am- Crew will begin laying pipe today on up A line from MH A12 location. 

Blasting will also occur today with gas truck just arriving onsite. 

8:10am- back to breaking rock...

9:04am- 1st joint for today in place. 

10:40am- Del-Sha crew at E line creek crossing today to begin bore. Chris from Flatcreek has come and figured grade to cross creek and has decided to keep it at plan grade of .40%. 



1:00pm- A line crew has now laid their 2nd joint for today while rock breaking continues. 

1:35pm- Joint 3 getting placed. 

3:40pm- a lot more rock breaking has occurred. 4th joint now getting placed. 

4:45pm- issue with breaker now so crew puts lid on MH A12 to round out the day. 