Turkey Creek Ph 1 - Flat Creek (Line Work)


8:15am- crews arriving onsite now due to a delay because of the rain this morning.  
8:45am- Pipe now going back into casing here at RR03 under rain showers. 

9:40am- 48 more feet and pipe will be back in casing. 

10:15am- pipe is in now as tracer wire is getting pushed through. 

11:00am- Boot is on casing and crew will begin to make connection at MH A11. 

12:55pm- 2nd joint going for connecting to MH A11. 

1:30pm- A total of 32.25’ of PS46 27” pipe makes connection to bore from MH A11. 

2:00pm- Pipe now getting graveled. 

2:35pm- gravel now complete. 

3:30pm- backfill continues after manhole wrapping and strapping. 

5:00pm- the majority of the huge pule adjacent to MH A11 is almost gone now. Crews will return tomorrow to start at MH A12. 