Friday, June 12, 2020

Turkey Creek Ph 1 - Flat Creek(Line Work)


7:10am- crew will work to lay more pipe today on A line. 

7:50am- already having to break rock...

8:30am- 1st first now in place for today. 

9:15am- 2nd joint now in. 

10:10am- 3rd joint now in place along with a trench seal to help keep back the water. Upstream at this point, there is hardly any water coming into trench; its all coming from behind them. 

10:15am- Iowa Trenchless is formed up and will pour the thrust block and headwall this afternoon at RR02 bore site. 

10:45am- Del Sha is now reaming back with the 36” head hoping to be done today with that. 

11:00am- 4th joint now in as crew has now moved the pump forward. 

11:55am- 5th joint in, and rock breaking resumes. 

12:50pm- 6th joint now placed. 

2:10pm- 7th joint now placed. 

3:05pm- #8 now in place. 

4:15pm- 9th and final joint for today. Backfill will now occur. 