Monday, June 15, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:20am- more pipe work on “A” line. Crew is shooting for getting to MH A13 location today. 

Also Del-Sha will continue to pull 42” reamer  hopefully getting it done today and Iowa Trenchless will begin boring at RR02. 
8:20am- joint #1 now going in for the day. 

9:00am- #2 joint now placed. 

9:30am- 3rd joint in and ready for gravel. 

9:55am- solid rock has shown up again. Just not blasted good...

10:40am- 4th joint has been placed and digging for 5th. 

10:55am- 5th now getting placed. 

12:05pm- Iowa Trenchless are now boring at RR02. Cutter is still in concrete head wall. No casing is in yet. 



12:50pm- Del-Sha is still reaming back with the 42” reamer. 

1:30pm- joint #8 is now getting placed. 

2:55pm- 9th joint in as crew moves water pump. 

3:55pm- 10th joint now in. 

5:15pm-more rock breaking has occurred as the crew moves pump again. No more pipe will be laid today. A total of 10 joints are laid today. 