7:20am- more pipe work on “A” line. Crew is shooting for getting to MH A13 location today.
Also Del-Sha will continue to pull 42” reamer hopefully getting it done today and Iowa Trenchless will begin boring at RR02.
8:20am- joint #1 now going in for the day.
9:00am- #2 joint now placed.
9:30am- 3rd joint in and ready for gravel.
9:55am- solid rock has shown up again. Just not blasted good...
10:40am- 4th joint has been placed and digging for 5th.
10:55am- 5th now getting placed.
12:05pm- Iowa Trenchless are now boring at RR02. Cutter is still in concrete head wall. No casing is in yet.
12:50pm- Del-Sha is still reaming back with the 42” reamer.
1:30pm- joint #8 is now getting placed.
2:55pm- 9th joint in as crew moves water pump.
3:55pm- 10th joint now in.
5:15pm-more rock breaking has occurred as the crew moves pump again. No more pipe will be laid today. A total of 10 joints are laid today.