Tuesday, June 23, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


6:45am- Iowa Trenchless has 80’ of casing in now of the 108’ needed for this RR02 bore. Crew will weld up 5th section today and continue on. 

7:45am- line crew still pumping water so that the first joint for today can go in. 

9:00am- 1st joint of the day goes in. 

10:45am- crew digging out for MH A14. 

11:35am- 2nd joint now placed along with MH A14 base for measurement of last piece of pipe to join them together. 

12:20pm- MH A14 base and a total of 35.5’ of pipe is laid connecting it to line A today. 

Line is also lamped by laser back to MH A13. 
1:45pm- excavator digs at MH A15 site to see how much water they are going to encounter...
Its a bunch!

2:25pm- MH A14 is getting wrapped and strapped. 
3:20pm- backfill occurs at MH A14. 

4:15pm- another section on and wrapped with strapping to follow. 

4:40pm- strapping now done. Backfill to finish out the day. 