Thursday, June 25, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


6:45am- Del- Sha will continue to ream hole today at creek crossing between MH A24-25. 

7:15am- Flatcreek will continue to lay pipe upstream of MH A15. 

8:30am- still pumping water this morning...backfill continues in the meantime. 

9:30am- joint #1 is now in place. 

10:00am- a partial joint, 6’ is added in. 20’ now placed. 

10:35am- 2nd full joint now in. 34’ total so far. 
11:55am- I have contacted Chris for the second time requesting that the metal straps from the pipe bundles be picked up immediately before any more top soil goes down. Also reminded him that Flatcreek will be responsible for the damage to the  owners equipment when it happens due to straps left and buried onsite!

12:10pm- 4 joints now laid + the 6’ piece for 62’ laid so far. 

1:15pm- 76’ of pipe now laid 

1:50pm- 6 joints + 6’ now equals 90’ laid so far. 

2:20pm- 104’ now laid in place. 

3:00pm- 118’ now laid. Backfill occurs in the background. 

3:30pm- 9 joint + the 6’ piece now equals 132’ laid in place. 

4:20pm- 10 joints laid today + the 6’ piece =146’ of 27” ps46 pipe. Crew will continue with backfill to round out the day. 

4:45pm- Del-Sha still reaming, not with the 24” reamer. All appears to be going good. 