Wednesday, June 3, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


6:55am- All crews onsite this morning. Flatcreek & Iowa Trenchless are at RR bore 3 and I seen Del Sha go through town this morning headed towards their spot to begin the Creek Crossings starting at MH A26 for E line. 
No pipe was pulled from Bore 3 last night...

8:20am- pipe is now getting pulled out of RR03. 
10:05am- all of the pipe is now out and is now getting cleaned. 

Bore casing is also getting water pumped through it to get it cleaned up. 



11:00am- area of creek crossing for E line and at MH A26 respectively. 



11:50am- new spacer now getting placed onto carrier pipe. 

1:25pm- Casing is now clean and new spacers are being fastened to the pipes. 



3:00pm- now that the brief rain shower is over, crew has resumed their welding of the guide rail inside the casing and vent pipes will be made up also. 

4:40pm- vent pipe now on downhill side of bore casing. 

4:50pm- Crews have decided to weld up vent on opposite side now and begin pushing pipe tomorrow. 