Tuesday, June 2, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:00am- Flatcreek onsite to do clearing for E line. Also Iowa Trenchless to be onsite to redo pipe in casing at RR bore 3. 
7:40am- Blasting holes are drilled and ready from MH A16 to MH A14 area and are awaiting gas truck. 



9:45am- still awaiting Iowa Trenchless. 


12:50am- Well, unfortunately there is nothing more to report at this point. Iowa Trenchless is supossed to be here just anytime now....

2:50pm- Iowa Trenchless has arrived onsite finally, but now its going to be just a little bit before pipe starts coming out of the bore...

4:30pm- 4” pump is now pumping water on MH A12 side. 

5:10pm- Iowa Trenchless is now onsite at quitting time to work... I have called Chris to let him know that he needs to manage this situation and to contact property owner about having a crew onsite late. Pipe to be removed tonight and new Spacers to be installed tomorrow. 