Monday, June 29, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:00am- Del-Sha are still reaming this morning. Getting closer to getting the hole ready for casing here at MH A24-25. 

7:15am- water is pumped down here on A line between MH A15-16 area. Crew will lay pipe today. 

8:45am- 1st joint now getting placed. 

9:20am- 2nd joint in place. 

10:20pm- 3rd in place. 

11:20pm- 4th joint placed. 4” Water pumps had to be switched out due to an issue with the diesel pump. 

12:50pm- Rock had to be broke out for next joint. 

1:45pm- 5th joint in place, now more rock is to be broke. 

2:15pm- 6th now placed. 

3:00pm- 7th joint getting placed. 

3:30pm- casi g is across the creek now at MH A24- 25. 



4:00pm- Grades are shot on casing. 

4:40pm- water is running the right direction through casing. 

Laser was also placed to ensure alignment of the casing. 

5:10pm- line crew is preparing to bed their 9th and final joint for the day. 