Wednesday, June 24, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


6:50am- Iowa Trenchless appears to be done with this bore here at RR02. Carrier pipe to be installed today. 

7:35am- Del Sha is starting their 2nd creek crossing today at MH A25 - A24. 

8:10am- Flatcreek finishes MH A14 with placement of lid; wrapped and strapped. 

Hole is pumped down at MH A15 location. Crew will dig out and set manhole to start this section of pipe. 

9:50am- crew pulls tape and drops a rock for center of manhole, making sure circumference of hole is dug out enough. 

10:50am- MH A15 base now placed. 

11:00am- Del-Sha has made it across with the pilot hole and are now pulling back with first reamer. 

1:20pm- carrier pipe is getting loaded into casing at RR02 now. MH A6 side will be 4 hundredths low and A7 side will be near spot on. 

1:45pm- Laser is setting in pipe at RR02. GRADE BY LASER is .72%. 



2:25pm- 4 joints now in at MH A15. More gravel has been requested for top of pipe so that it is level across ditch, not domed. 

3:15pm- 5 joints now placed. 

3:45pm- 6th now in place. 

4:35pm- joint 7 now placed. Crew will finish out the say backfilling. 



5:00pm- Del-Sha still pulling back on the first pass with the 18” reamer. 