Thursday, June 18, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


Crews will continue working at their respective places. Flatcreek laying pipe on A line; Del-Sha will finish up E line creek bore; Iowa Trenchless will keep boring at RR02. 
7:05am- Del-Sha pumps water so that we can shoot grade in casing this morning. 

9:00am- So, with much debate, the casing has shown that it is 11” high on MH E1 side. Del-Sha will pull out casing and begin drilling again to lower hole in same location. 



9:15am- pipe crew has 2nd joint going in place now. 

10:30am- 3rd joint now placed. 

10:55am- 4th now in place. 

11:40am- 44’ of casing in now at RR02. Crew says it is going well!

1:10pm- 5th joint in and digging for #6. 

1:50pm- 6th joint in. 

2:20pm- 7th joint in as crew prepares to move water pump. 

3:00pm- #8 now in place. 

4:05pm- crew has laid their last and final joint for today. 9 joints or 126’ of 27” PS46 pipe laid today jere on A line. 