Friday, June 5, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


Crew will try and get MH A12 set today and tied in at Bore. 
7:05am- 6” pump will replace the 4” pump here at MH A12. 4” pump is not keeping up with the water coming in at this time. 

8:15am- water is almost pumped down here at MH A12 location. 

9:00am- crew will be reinstalling boot around casing and pipe. 

11:05am- after some rock breaking the crew is now preparing to set MH A12 base. 

11:50am- Bore for RR02 is getting dug and benched. Iowa Trenchless is wanting to work on Saturday so I have instructed Chris with Flatcreek ti make sure all property owners are good with it and to get an email to the engineer for Owners approval. 

12:30pm- base to MH A12 is getting placed now. 
1:45pm- 19’ of PS46 27” has now completed the tie in to RR03. 

3:00pm- barrel section on MH A12 now and grade of flowline is checked against benchmark. There is a .29 difference with manhole being low. 


-3:40pm: just received word that Iowa Trenchless is now going to pull out today and wont be back until Monday or Tuesday of next week. 

4:00pm- alignment to the next manhole done and rock just got broke out for first joint out of MH A12. 

5:30pm- MH A12 now wrapped and strapped on bottom section with a joint of pipe now headed upstream. A total of 33’ of PS46 27” pipe laid today and MH A12 set. 