Wednesday, June 17, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:10am- Line A work continues with the excavator being repaired late last night. 

7:40am- 1st joint now laid out of MH A13. 

9:15am- 2nd joint in now. 

10:05am- 3rd joint in and digging with ripper now to tear out rock layer. 

11:05am- 4th joint in and rock breaking had to occur for the next joint. 

12:00pm- 5th joint now in place. 

1:00pm- 6th joint now in. 

1:30pm- 7th joint in place. 

2:20pm- while rock is getting broke out, MH A13 is getting wrapped and strapped rest of the way up. 

3:00pm- 8th joint and pump is getting moved again. 

4:20pm- 9th joint going in. 

4:50pm- crew stops at the 9th joint today due to rock. Backfill is underway now to round out the day. 