7:05am- crew is back on Line A today to lay more pipe.
9:20am- crew has finally laid their first joint for today!
10:00am- 2nd joint now in place.
12:05pm- 3rd joint now in. Still breaking rock today...
1:40pm- 4th joint getting checked and gravel will be going on it next.
2:35pm- 5th joint now getting placed.
3:40pm- 6th joint getting laid.
4:35pm- Still having to break rock...backfill occurs though while rock is broke.
5:15pm- 7 joints laid today. Crew will finish graveling and then backfill this joint and call it a day.