Tuesday, July 21, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:40am- crew was s back to E line crossing today to begin loading casing with pipe and start making the creek crossing tie ins. 

8:45am- spacers now getting installed on carrier pipe for E line crossing. 

10:20am- loading casing for E line crossing now. 

11:35am- pipe is now all loaded into casing on line E creek crossing. 

1:10pm- gravel will begin going in to get grade for pipe. 

1:45pm- a couple of joints in coming out of MH A26. 

2:35pm- MH A26 is now connected to the creek bore crossing headed to MH E1 location. 

2:50pm- boot getting installed from casing to carrier pipe. 

3:45pm- line is backfilled for now. Crew will move to west side of creek and begin moving bore pit spoils so work for MH E1 can begin tomorrow. 



5:20pm- Iowa Trenchless is now onsite at RR01 here at the WWTF. Equipment is getting moved in and set up today yet. 