Monday, August 3, 2020

Turkey Creek Ph 1 -Flat Creek (Line Work)


6:35am- Iowa has 46’ of casing in now as they worked last Friday. 

7:20am- pipe to come back out and get reset to right grade once laser is set back up after recalibration. 

8:00am- crew went back to MH A15 and removed top and barrel section so bore machine can line up over manhole for this creek bore back to A14. 

9:10am- 4 joints have now been removed between casing and MH A25. 

9:35am- grade is shot and distance measured; new grade is .23% for the last 100’ to manhole 25. 

10:10am- ditch will now be getting cleaned out. 

10:50am- 2joints laid back in place now. 

11:45am- 3 joints now placed. 

12:50pm- getting close to MH A25 now. 

1:45pm- measurements are taken for the short puce of pipe. 

2:20pm- crew is cutting back bench in this drop manhole so that pipe can be inserted in far enough to get it connected to pipe line. 



3:50pm- final touches are put on invert before pipe is pushed into MH A25. 

4:40pm- pipe now connected to MH A25 as gravel gets placed. 