6:50am- crew will continue with cleanup at MH A27,26, and E1 working their way down line. Brush pules will also be getting burned as they progress. Crew will also be continuing grouting of manholes.
7:00am- Del-Sha has chosen to bore a pilot hole above the current hole here at creek crossing A15-14. They will then pull back an 18” reamer to cut out the top of hole so that the casing can be raised up.
7:30am- crew currently moving the 4” pump from MH A20 and will place it at MH A9 so that grouting can continue from MH A13 downstream.
Casing at MH A18-19 will also be getting pulled back through the bore this morning.
7:50am- Iowa Trenchless is pulling casing to get to the cutting head today. They feel there is an issue with it as its not cutting as expected.
12:40pm- brush piles are burning as crew continues their cleanup work here around MH A27, 26 and E1 respectively.
2:00pm- casing has been pulled all the way back through bore at A18-19. Still more hand work needed to get casing to be on grade.
2:05pm- more work continues in manholes this afternoon. Crew a MH A13 now and will continue downstream today.
3:30pm- MH A13 flowline and pipes are now grouted.
4:25pm- MH A12 now getting groute around pipes.
5:05pm- crew will clean up tools and call it a day. Flowline is yet to be done here.