7:05am- spoke with Iowa for a bit this morning about the bore. They have cut out relief holes in the casing on the bottom to allow the fines a way out instead of getting trapped under the casing, thus raising it. Hopefully this helps as they are currently running at about .8%.
7:35am- Water is getting pumped this morning as Del-Sha is set back up on MH A15-14 to continue with this bore.
7:45am- Also pumping water at MH A16-17. Once water is down here Del-Sha crew will do some hand work to remove some rock from top of bore on MH A17 side.
8:10am- Flatcreek crew will be putting on spacers for the next creek crossings.
9:30am- crossing 18-19 now has spacers installed on pipe.
9:45am- Del-Sha is inside bore removing rock from the top of it at creek crossing 16-17.
Also at this time more spacers are going on pipe for this crossing.
10:45am- more spacers now for creek crossing 14-15.
11:55am- spacers installed. Crew is calling it a day due to no more work can be done at this time.
12:25pm- Bore machine back operating at this time here at RR01.
Also electrician is working on Liftstaion today.
1:05pm- I will now be offsite.