Thursday, August 6, 2020

Turkey Creek Ph 1 - Flat Creek(Line Work)


7:05am- spoke with Iowa for a bit this morning about the bore. They have cut out relief holes in the casing on the bottom to allow the fines a way out instead of getting trapped under the casing, thus raising it. Hopefully this helps as they are currently running at about .8%. 

7:35am- Water is getting pumped this morning as Del-Sha is set back up on MH A15-14 to continue with this bore. 

7:45am- Also pumping water at MH A16-17. Once water is down here Del-Sha crew will do some hand work to remove some rock from top of bore on MH A17 side. 

8:10am- Flatcreek crew will be putting on spacers for the next creek crossings. 

9:30am- crossing 18-19 now has spacers installed on pipe. 

9:45am- Del-Sha is inside bore removing rock from the top of it at creek crossing 16-17. 

Also at this time more spacers are going on pipe for this crossing. 

10:45am- more spacers now for creek crossing 14-15. 

11:55am- spacers installed. Crew is calling it a day due to no more work can be done at this time. 

12:25pm- Bore machine back operating at this time here at RR01. 

Also electrician is working on Liftstaion today. 

1:05pm- I will now be offsite. 