Thursday, August 20, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


6:35am- Iowa will add casing and begin cutting again today. They are currently at 85’ or so. 

7:30am- more cleanup will occur on Rittenhouse today. Manholes on the 12” section will begin getting grouted and equipment will be moved to MH A28-29 area so the line can be installed there. 

8:10am- Log pile is lit on fire. Rittenhouse did not want the Sycamore tress. 

8:35am- Creek Crossings are still being worked on. 

9:00am- Manholes on 12” line are getting grout today. 

10:00am- MH A33 now grouted. 

11:10am- MH A34 now grouted. 

12:30pm- MH A35 nearing completion. 

2:00pm- MH A36 getting grout. 

2:35pm- MH A36 now finished. 

3:05pm- MH A37 now grouted. 


3:30pm- equipment is getting moved over to Substation area so work can start next week to finish out the 12”. 

4:45pm- Iowa has achieved nearly 20’ today! Crew plans on working tomorrow and Saturday. 