6:35am- Iowa will add casing and begin cutting again today. They are currently at 85’ or so.
7:30am- more cleanup will occur on Rittenhouse today. Manholes on the 12” section will begin getting grouted and equipment will be moved to MH A28-29 area so the line can be installed there.
8:10am- Log pile is lit on fire. Rittenhouse did not want the Sycamore tress.
8:35am- Creek Crossings are still being worked on.
9:00am- Manholes on 12” line are getting grout today.
10:00am- MH A33 now grouted.
11:10am- MH A34 now grouted.
12:30pm- MH A35 nearing completion.
2:00pm- MH A36 getting grout.
2:35pm- MH A36 now finished.
3:05pm- MH A37 now grouted.
3:30pm- equipment is getting moved over to Substation area so work can start next week to finish out the 12”.
4:45pm- Iowa has achieved nearly 20’ today! Crew plans on working tomorrow and Saturday.