Friday, August 28, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


6:30am- Iowa welding on another casing this morning. They are at 165’. About 2-3’ and they will be punched through into over blasted area on receiving side. Then they should be able to add last casing and push rest of the way. 

7:15am- Del-Sha now has casing pulled back into bore at MH A14-15. Flatcreek will shoot grade on it here shortly to see if they can get enough grade now through casing. 

8:30am- MH A15 side of casing about 1/2” high. Gravel will be placed at bore around casing and then the other side will be raised slightly. 

10:05am- casing is now at necessary grade to match both manholes. The laser is showing a .70%. A bucket of water was just dumped through casing to ensure flow. 

10:45am- setting up to shoot grades on casing at bore on MH A18-19. 

12:30pm- the laid pipe from MH A17 on the last couple of joints appears to have floated up about 2” or so. Casing also has a sag of 7” in it. Crews are trying to figure out what exactly to do. Pipe will foresure have to be dug up and reset. 

12:40pm- seeding s occurring on Rittenhouse today in area of MH A25-27&E1. 



1:40pm- Crew back over at MH A28 area to continue with cleanup. Open cutting creek crossing A18-19 is currently being discussed. More to follow next week. 

2:00pm- Ill be offsite rest of the day. 