Tuesday, August 18, 2020

Turkey Creek Ph 1 - RL Persons (L.S.)


Start up on the Lift Station will occur today at 9:00am. 
8:00am- Electricians, JCI, and RL Persons are onsite for start up. 

8:50am- TCRSD crane truck is here and set up for lowering pumps into wet well today. 

Name plates for pumps:
Pump 1-

Pump 2-

9:15am- there is an issue with how the VFD’s are wired Dale said. Once they get this figured out the startup will occur with Gary from JCI. 

10:15am- All is wired correctly now and pumps are set at 45Hz for 600 gallons per minute. With them cranked all the way up to 60Hz, they pumps should produce 2000+ gpm. 

12:00pm- Start up went well after wiring issues were resolved. Some small items need attention that RL Persons will handle when they come back for final. 