Start up on the Lift Station will occur today at 9:00am.
8:00am- Electricians, JCI, and RL Persons are onsite for start up.
8:50am- TCRSD crane truck is here and set up for lowering pumps into wet well today.
Name plates for pumps:
Pump 1-
Pump 2-
9:15am- there is an issue with how the VFD’s are wired Dale said. Once they get this figured out the startup will occur with Gary from JCI.
10:15am- All is wired correctly now and pumps are set at 45Hz for 600 gallons per minute. With them cranked all the way up to 60Hz, they pumps should produce 2000+ gpm.
12:00pm- Start up went well after wiring issues were resolved. Some small items need attention that RL Persons will handle when they come back for final.