7:00am- Iowa has found that the “shoe” that they put on the casing to help steer it has broke loose. They will fix it first thing this morning. They will only work a half day due to driving back to Iowa for the weekend.
7:20am- Del-Sha has casing welded back ip and it will be pulled back into place at creek crossing 18-19. We will then shoot grade to get it where it needs to be.
Flatcreek to groute more manholes today also.
9:40am- Del-Sha has decided to do some hand work in bore before pulling casing to ensure we have the needed clearance.
9:45am- Flatcreek crew digging at MH A22 to locate tracer wires so that lid can be mounted during grouting.
10:40am- wire is located and brought back to the top. Backfilled again.
10:50am- crew now at MH A23 to groute it.
11:20am- flowline work occurring.
12:15pm- crew is calling it a day. Influent pipe will still need groute placed around it jere at MH A23.