6:35am- Iowa is pulling all casing and cleaning bottom of bore hole as they are pulling it out. Once finished they will begin to reassemble things and hopefully be boring again tomorrow. They are hoping by cleaning the fines out from under the casing they can get the grade to flatten out some.
7:05am- casing has been pulled back through bore at creek crossing MH A16-17. Crew will now work to get Casing to grade.
7:40am- grades are checked on casing. Needs to be raised on one end and lowered on the other.
9:00am- gravel is placed at each end of casing now and final adjustments are underway.
10:35am- crew now at MH A17 preparing to lay pipe back towards creek crossing.
11:30am- 1st joint laid downstream of MH A17.
12:55pm- 2nd joint in now.
1:55pm- 3rd joint now placed as gravel is graded out for 4th joint.
2:45pm- 5th joint now being placed. Crew is right at having to dig from the side to get both ditch lines tied together.
3:10pm- 1st casing going back in now at Iowa’s bore.