Monday, August 17, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


6:45am- Iowa Trenchless is not onsite yet this morning due to driving back in from Iowa. Rail Pros Inspector is not onsite at this time either. 
7:30am- Creek Crossing A18-19 Is needing more work on top of hole today. 

7:40am- crew is shooting grade at MH A14-15 creek crossing to see if Del-Sha has hit their mark or not. 

8:00am- MH A14 side is good, but A15 side is low by at least 14”. Del-Sha will be deciding on how they want to proceed. 

8:45am- crew back working on manholes today until MH A19 gets re-staked this morning so digging can continue. 
MHA23- flowline work,  and out pipe to the trimmed back. 

9:50am- now working on grouting A22. 

12:15pm- Flowline and pipes now grouted. 

1:30pm- crew has moved to MH A26 to remove excess pipe on influent side so that grouting can happen. 

3:45pm- A26 is now grouted. Drop on 12” is still yet to do. 

4:00pm- D6 angle blade dozer is now onsite to aide with cleanup. Cleanup begins here at MH A26 to get a final sweep done before seeding season begins. 

5:00pm- crew calling it a day. 



5:25pm- Iowa arrived around 1pm today and is having trouble pulling casing due to the cutting head not turning as of right now. They will set the machine tomorrow and try turning it again before removal to put new carbide cutters on it. 