Tuesday, August 11, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


6:45am- Iowa is welding on the their third casing. Once pushed in this will put them back to the 60’ they were at before. 

7:15am- crew will put carrier pipe into casing today and get it tied to line going to MH A17. 

7:50am- grade is shot on pipe and casing one more time to make sure it will all tie together. 

8:45am- carrier pipe going back in casing now at MH A17-16. 

9:35am- crew will have to remove one spacer to get pipe to align in casing on MH A17 side. 

10:00am- pipe is now joined. 

Half of the spacer will be inserted under the pipe now. 

10:10am- casing to pipe seal is now installed. 

10:20am- pipe getting gravel now. 

10:30am- Flowable fill going in around casing. 

11:50am- MH A17 getting wrapped and strapped. 

...and trench seal is getting poured on MH A17 side also today. 

12:10pm- rain begins. Crew calling it a day. 















No comments:

Post a Comment