6:45am- Iowa is welding on the their third casing. Once pushed in this will put them back to the 60’ they were at before.
7:15am- crew will put carrier pipe into casing today and get it tied to line going to MH A17.
7:50am- grade is shot on pipe and casing one more time to make sure it will all tie together.
8:45am- carrier pipe going back in casing now at MH A17-16.
9:35am- crew will have to remove one spacer to get pipe to align in casing on MH A17 side.
10:00am- pipe is now joined.
Half of the spacer will be inserted under the pipe now.
10:10am- casing to pipe seal is now installed.
10:20am- pipe getting gravel now.
10:30am- Flowable fill going in around casing.
11:50am- MH A17 getting wrapped and strapped.
...and trench seal is getting poured on MH A17 side also today.
12:10pm- rain begins. Crew calling it a day.