Thursday, August 13, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work (


12:00pm- Iowa is back turning again after removal of augers this morning to make adjustments inside casing. 

12:20pm- Flatcreek crew working on grouting manholes today and other odd and ends. Staking for MH A19 is needed before laying pipe from MH A20 downstream to A19 at creek bore. 





Working on A 25 now. 

MH A27 

1:45pm- MH A25 flowline and pipes now grouted. 

1:50pm- Crew now working on A24. 

3:00pm- MH A24 now grouted in. 

3:10pm- grade has been shot on creek crossing casing again today and it still needs a couple of inches taken from the top of the bore. Casing to be pulled and work to proceed. 

4:10pm- crew now at MH E1 to groute downstream pipe only due to this being a “tie in” manhole. 

4:30pm- MH E1 now grouted. 

5:30pm- Iowa stated tonight that they are in about 80’ total, but casing is in about 75’ due to the cutting head. 
Augers will be pulled in the morning and casing checked and then resume cutting. 