6:40am- Iowa has water in their pit this morning as they are approaching the other side at about 165’ in so far. The entire line is draining to this pit now.
7:10am- crew back laying line near MH A28. Encasement and slope anchor to be poured today.
8:30am- rebar is now in place for 30’ encasement later today.
10:00am- slope anchor rebar going in place.
11:20am- concrete going in at slope anchor now between MH A29-30.
11:50am- encasement now getting concrete between MH A29-28.
12:15pm- now completed.
1:00pm- excavator has a track off and the crew will work to get it back on.
4:40pm- MH A28 is set and 12” line is all tied together
including the bore.
More gravel to be applied, then backfill.