Thursday, August 27, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


6:40am- Iowa has water in their pit this morning as they are approaching the other side at about 165’ in so far. The entire line is draining to this pit now. 

7:10am- crew back laying line near MH A28. Encasement and slope anchor to be poured today. 

8:30am- rebar is now in place for 30’ encasement later today. 

10:00am- slope anchor rebar going in place. 

11:20am- concrete going in at slope anchor now between MH A29-30. 

11:50am- encasement now getting concrete between MH A29-28. 

12:15pm- now completed. 

1:00pm- excavator has a track off and the crew will work to get it back on. 

4:40pm- MH A28 is set and 12” line is all tied together 
including the bore. 

More gravel to be applied, then backfill. 