Monday, August 31, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


6:40am- Iowa finished bore late last Friday. They will return after Labor Day to install carrier pipe and spacers. 

8:00am- crew is moving equipment around and will begin loading carrier pipe in creek bore @ MH A14-15 here shortly. 

9:55am- welder has finally arrived onsite to weld the guide rail in the casing so that the pipe and spacers can be installed. 

11:20am- welding is done on guide rails as crew checks grade one mor time with laser. Shows .70%. 
Carrier pipe placement will now begin. 

11:40am- 1st joint going in as tracer wire gets attached. 

1:30pm- pipe is now through casing. 

2:25pm- gravel going down for rest of pipe to connect MH A14 to bore. 

3:15pm- Bore is now connected to MH A14. Boot and gravel to be applied next. 

4:15pm- work has stopped at A14-15 so that crew can shoot grade at MH A8-9 for final creek bore. 