6:40am- Iowa is now at 145’. Another piece of casing will be welded on and boring will continue.
7:10am- crew back working on Line A at MH A29-30 breaking rock.
9:00am- MH A29 base now set in place. Gravel will go down next for line to be laid between the two manholes.
10:15am- 2nd joint in upstream of MH A29. Slope anchor area dug as well.
11:55am- MH A29 now tied to A30 with pipe. Area left not graveled is for slope anchor.
12:05pm- two joints now laid downstream of MH A29.
2:05pm- pipe now down to encasement area crossing dry creek at STA 114+50.
3:50pm- backfill of line laid today is underway and cages for encasement of pipe are getting built.
4:30pm- appears Iowa has achieved another 12-15’ today at this time.