6:55am- Iowa will set bore machine back in pit this morning and continue with yesterday’s plan of pulling back casing and trying to recut rock to get casing to come down some.
7:30am- Blasting crew will be shooting out to approximately STA 15+50 today from MH A3 location.
8:10am- Del-Sha is set up back in n MH A17-16 creek bore to try and ream it more today.
Flatcreek crew will be taking care of any issues that have been lingering and will be also bolting down the Bolt down rings and lids today on all manholes previously set.
10:30am- Blasting just occurred on Rittenhouse from MH A3 to nearly STA 15+50.
12:05pm- frame and lid work still occurring.
1:15pm- still bolting down lids.
2:45pm- Drilling to finish up area to blast. Near STA 15+50 to MH A6. This should be the last of the blasting on this project once shot is done.
3:45pm- Iowa has not turned the bit any today after all. They did pulled back 20’ of casing and have been, all day, working on the “cut outs” that help to steer the casing.
4:30pm- I’m headed offsite now.