Iowa has made steady progress from last Friday and Saturday’s work. Crew is pulling augers this morning to make adjustments in casing guides. 125’ in so far.
7:25am- Flatcreek will begin work at MH A28 today to get the 12” line finished up this week.
8:35am- equipment now moving material around from blasting so that digging can begin.
9:55am- line work begins at MH A30 working downstream.
11:05am- digging out still for line, slope anchor and MH A29.
1:00pm- crew has stopped working due to the jackhammer not functioning. Crew is figuring out what to do next.
1:40pm- dozing on cleanup will continue on Rittenhouse and more manholes will get grouted to round out the day.
2:40pm- MH A17 is getting grout at this time.
4:14pm- MH A17 now grouted.
4:50pm- Iowa has about 135’ or so in now.