Thursday, April 30, 2020

Turkey Creek Ph -1 Flat Creek (Line Work)


7:20am- crew back to lay pipe today as waters have receded. 

8:30am- joint #1 in being placed. 

9:45am- joint 2 now in place. Pump at MH A25 had to be readjusted. Hose was in to much silt. 

10:35am- crew has hit rock and will need trackhoe and hammer of which are here at the top. Crew picking up barrel section for MH A26 while here. 

11:30am- breaking rock now. 

12:30pm- still breaking rock...

2:15pm- 4th joint now in and grading out for fifth.  

2:30pm- 5th now placed. 

3:15pm- joint 6 now in place. 

4:25pm- 7th joint now laid in place and will be the final one for today. Ditch will be backfilled to round out the day. 
















Wednesday, April 29, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:35am- Holes are full this morning as pumping is underway. 



8:45am- crew is preparing to call it a day due to the amount of water that continues to be pumped. The 4” and 6” pumps will continue to pump today to try and catch up. 

9:35am- work Layton’s property moving pipe and moving topsoil will continue rest of the day no pipe to be late today. 


Tuesday, April 28, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:25am- crew bedding for 1st joint to be laid. 

7:30am- Placing joint #1 for the day. 

8:20am- joint #2 now going in place. 

9:00am- Breaking rock for 3rd joint. 

More backfill occurs. 

9:50am-3rd joint getting graveled up. 

10:35am- 4th joint now that n. 

11:15am- crew has had a mishap...last joint laid was high and they tried to pull it out to redo it and two joints came instead of the one. 



Gravel removal now occurring. 

11:40am- the resetting of joint 3 now done as gravel goes back over pipe. 

12:05pm- joint 4 now back in place. 

1:20pm- Joint 5 makes its way to the ditch finally.

2:00pm- 6th joint now laid. Had some issues with laser, but crew has a fan running pulling air through pipe now. 

2:40pm- joint #7 now going in. 

4:15pm- joint 8 makes its way to the ditch after more laser issues. 

4:25pm- with about 120’ of ditch to back fill the crew has stopped laying pipe for the day. 8 joints or 112’ of 27” laid today. 


















Monday, April 27, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:10am- water is pumped down at this time and crew will begin laying pipe on towards MH A26. 

8:00am- some hoses have been changed out on the 360 excavator and it will now be back in use today. 

8:45am- 1st joint of the day!

9:20am- 2nd joint going in. 

9:45am- 3rd going in. 

10:25am- 4th joint. 

10:50am- ditch caves in on 5th joint setting... will now be pulled out. 

11:05am- 5th joint now in place. 

11:35am- 6th joint now in place. 

12:05pm- 7th joint getting placed. 

12:55am- rock is being broke out as backfill begins. 

1:40pm- 8th joint going in now. 

2:40pm- still breaking rock for the 9th joint...

3:20pm- 9th joint going in. 

4:00pm- joint 10 now going in. 

5:00pm- crew is calling it a day as more backfilling occurs. Also starting to rain now. 10 joints for todays total.