Turkey Creek Ph 1 - RL Persons (L.S.)


6:40am- 8’ of water in hole this morning as crew has it almost pumped out already. The bituminous coating will begin today and a clean gravel backfill may begin. 

More ductile work to continue as well. 

11:30am- Tie in at head works is now completed. 

1” clean rock is going in around wet well now as crew continues to double coat the walls. 





5:00pm- RL Persons will barrow a stick of 27” from Flatcreek so that they can work on getting MH A1 set maybe tomorrow. 

5:30pm- rock placement around the Liftstaion walls is going good, but slow. 

Rest of the ductile tying into headworks is mocked up now. Crew will finish installation tomorrow. 