Wednesday, February 19, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


8:00am- Pump was froze up this morning and crew had to unthaw it with torch. Back to digging now and more rock will need broke out upstream of MH A20. 

8:55am- still breaking rock. 

10:15am- Iowa Trenchless is onsite at power substation location. Flatcreek will use their trackhoe to begin digging bore put at tunnel area. 

11:55am- 28’ of 27” pipe laid, but not completely covered with gravel yet. John Escobar is onsite and making changes to the day. Gas truck is not going to come tomorrow due to roadway issues, so crew is going to be redirected to fixing roadway and staging more materials in the bottom area. 

1:30pm- bore pit RR-04 is getting dug out still. 



2:55pm- bore hole RR-04 is now cleaned out and ready for clean rock so that grade can be established. 

3:30pm- I’ll be headed now to the WWTF. 