6:50am- More ductile to be laid and concrete pour is on schedule for 10:00am today.
9:00am- gravel backfill going in trench in parking lot.
10:00am- Crew needs just a bit more time ... concrete put off til 11:00am.
11:40am- pour has started, concrete was tested with the following results; air 4.0%, slump 1.25”, temp 58*F. 2 gallons of plasticizer was added and slump went to about a 6” slump.
After plasticizer and priming of pump truck.
1:40pm- walls are now full and crew will work to smooth top and install keyway.
1:50pm- two area cuts in asphalt will get patched with concrete today.
2:00pm- asphalt patch repairs now poured with concrete.
Finish work yet to be done.
2:30pm- ductile line is covered with gravel, then backfilled.
4:30pm- patches are covered.
5:20pm- Box is now covered up.