7:00am- More forms to go up and digging in parking lot to locate line to tie in.
10:50am- line is now located in parking lot. Crew has shot grade on it and the ductile that is buried by the fence. 2’ difference of the pipe in parking lot being lower than the new buried ductile.
Concrete crew are inside the forms connecting them with supports.
4:25pm- 60 more feet of ductile is laid today as the Crew prepares to compact the trench.
Forms still going up on walls. Concrete to begin at 10:00am tomorrow.
4:40pm- I will be headed offsite to pick up concrete testing equipment for tomorrow.