6:45am- crews are on site today with rain falling. Work to begin on layout with string lines for positioning rebar mats on “mud pad” for floor. First though, pumping of water as hole is about half full.
7:30am- pumping water.
9:35am- Water is now pumped down and string lines are strung back at the top so that bottom alignment and layout can begin.
10:10am- I’ll be offsite to run to GRE office.
12:35pm- Back onsite now. Crew has wet well corners laid out as forms begin going up for floor.
1:30pm- benches going down before rebar mat.
1:50pm- rebar mat entering hole.
2:40pm- “L” bars now going in for uprights into walls as they are tied off to the supporting 2x4’s.
3:40pm- Most of the uprights are up now.
4:25pm- finishing touches for tonight occurring. Crew will pour tomorrow mid day if not sooner.