7:30am- spoke with Iowa Trenchless and they will be pouring head wall this afternoon possibly. Boring machine should be set on tracks today and the boring head is to be welded onto an auger stem.
Looks as though boring wont start until mid next week though.
No crew working for Flatcreek other than Blasters are to load and set off a shot in the bottom today at some point.
7:50am- just spoke with Richie on blasting time and they are loading holes now, gas truck is onsite. I will make my way down to see the blast this morning.
8:15am- holes are being loaded by gas truck now.
10:15am- loading the holes is going good. Crew will shoot in the next hour and a half possibly.
Here is what is left to load.
I will now be headed offsite to drop off cylinders to PPI.
1:20pm- Well, as you can see it has taken a lot longer than they anticipated...
3:05pm- Blasting now completed.
3:30pm- I’ll now be headed offsite