7:45am- crew getting laser set back up as more pipe will be laid today.
8:35am- 1st joint of the day now laid in place.
9:35am- 2nd joint of the day.
10:25am- 3rd joint now placed.
11:20am- 4th joint now laid and grade was shot at end of pipe with about 50’ to go to get to MH A21. They are about 3” low, but started at MH A20 1.5” low. So looking ok at this point.
1:00pm- 5th joint now in. Area of none graveled pipe is currently where the pump is sucking water from.
1:35pm- 6th joint being set.
2:20pm- 7th joint now being set.
3:15pm- 8th joint now laid in place as excavator digs out for MH A21.
3:55pm- Breaking rock for MH A21 while ditch is being backfilled.
4:40pm- 9th joint in for the day. A total of 126’ of 27” sdr35 laid today.
-Crew has stated they will work tomorrow beginning the day with setting MH A21 after more rock is taken out.
Crew will round out today with backfilling the ditch.