Tuesday, February 25, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:20am- crew to start back laying pipe today. More top soil is moved first thing for another shot on Friday. 

7:55am- more rock has to be broke out to get below flow line for gravel.  

9:50am- 14’ now laid in place. 

12:10pm- 6” pump was moved to fuel it and will begin pumping again shortly. 

12:45pm- back pumping now. Still only 14’ laid so far today. 

2:20pm- Two more joints now laid in place. Making it 3 now for today. 

3:50pm- 4th and possibly last joint of day. Total of 56’ of 27” sdr 35. 

4:00pm- A wall of rock is encountered and will have to be broke out. 

4:20pm- this will round out their day. No more pipe to be laid today. 