Crew will continue to haul out spoils from line work at substation area and grouting of manholes will begin.
8:20am- Spoils are getting loaded to be hauled offsite.
Also at this time grout mix has arrived onsite now and crew will soon begin grouting manholes. The line from MH A31 to A30 will be tested today at some point.
9:40am- Line passes air test from MH A31 to A30. Grouting will begin now.
10:45am- slow going today due to the grout not wanting to set up because of the cold. Still working on grouting 1st manhole of the day.
11:35am- Cleanup of spoils going well today. Upper portion of line done in area of MH A32-36 as excavator continues on lower portion in the same.
12:45pm- another manhole has grout now placed, but its still not setting up. Crew is going to call it a day until a different type can be purchased.
Haul out of spoils will continue this afternoon.
Ill now be headed offsite.