Tuesday, February 18, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


12:00pm- The scene at MH 20 location. 

1:10pm- MH A20 base is now set. 

2:20pm- an 8’ piece of 27” pipe is laid out of manhole. 

3:30pm- 1st full joint now laid, 22’ total. 

4:50pm- 2nd full joint now laid. 36’ total of 27” sdr35 pipe laid today. 

5:15pm- backfill of part of the ditch and fencing going up. 