7:35am - Flat Creek crew is continuing to break rock from from where they left off yesterday afternoon. Lots of ground water on site.
9:09am- Continue to break rock
10:27am- Set first two sticks of 27” sdr 35
11:48am- Continue to excavate dirt for pipe placement
2:00pm - 5 sticks of 27” sdr pipe installed
3:40pm - 6 and 7 27” sdr pipe for the day
5:16pm - Flat Creek finished the day with placing 126’ of 27”sdr pipe