Turkey Creek Ph -1 - Flat Creek (Line Work)


7:35am - Flat Creek crew is continuing to break rock from from where they left off yesterday afternoon. Lots of ground water on site.


9:09am- Continue to break rock



10:27am- Set first two sticks of  27” sdr 35 





11:48am- Continue to excavate dirt for pipe placement 
2:00pm - 5 sticks of  27” sdr pipe installed 
3:40pm - 6 and 7 27” sdr pipe for the day



5:16pm - Flat Creek finished the day with placing 126’ of  27”sdr pipe