Friday, February 28, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:15am- 2 man crew today will work on getting MH A21 set today and do backfill work. 

MH A21 location. 

8:35am- rock broke out now as excavator digs spoil out of the way. 

9:50am- water is now being pumped from hole. 

10:40am- water almost down now, but crew is working on cut off saw now as it wont stay running. 



12:10pm- well, no progress. Guys went and got another saw and are now back onsite. 

1:00pm- pipe has been cut to allow water in and installed in hole at MH A21. Gravel base is now down and grade is being figured out for manhole. 

1:10pm- grade is shot and MH A21 will be set consistent with what A20 was which is 1.5” low. I have also asked that they get a grade rod that is conducive to the “height”of the job needed. 

2:45pm- MH A21 base now set with 8.33’ of 27” sdr35. 

Pipe is lamped back to MH A20. 

3:00pm- crew will set barrel section and then move 6” pump up to this location and then backfill some. 

3:15pm- I will now be headed offsite. 