6:40am- Concrete and Pipe crew onsite today. 6” pump is now working and being used. Forms and steel to begin going in for walls and more piers to be dug out.
9:45am- ductile pipe going in so that alignment for rest of the piers can be done.
Rebar mats also going in on LS walls.
11:20am- ductile pipe is temporarily hanged to get placement of fittings so that piers can now be laid out to miss flanges.
Four mats of rebar are now in place.
3:10pm- piers are laid out for turn now by orange marks on the ground.
All eight rebar mats for the walls are in place. Corner rebar will begin getting tied into position.
5:35pm- 3 piers are now ready for concrete.
Corner bars are tied in now on south end of box.