Thursday, February 6, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:45am- crew will work to back fill around MH A37, then loadout trucks with spoils and testing should resume. 



9:20am- cone was s now placed and sealed up. 



10:35am- MH A37 now backfilled and testing is back underway, except there are issues with the testing equipment now...



10:50am- MH A34 has now passed vacuum test. More work to be done on testing equipment. 

12:50am- Line now tested between MH A33 & A34. Passes. 

1:10pm- MH A33 passes vacuum test. 

1:55pm- Line passes air test from MH A32 to A33. 

2:15pm- MH A32 passes vacuum test. 

3:40pm- Line passes air test from MH A31 to A32. 

3:50pm- MH A31 passes vacuum test. 

5:10pm- Line passes air test from MH A37 to A36. 

5:27pm- MH A37 passes vacuum test. 