6:45am- crews onsite and already pumping water.
Forms to be removed today and more digging on forcemain to occur.
12:10pm- crew has installed part of the fittings with valve attached
12:25pm- more pipe and another valve.
Forms being taking off at this time also.
2:05pm- “Tee”tie in to WWTF existing line is in place now, but not tied in yet. More ditch is opened to head towards new wet well.
4:20pm- more ductile laid this afternoon.
4:20pm- forms are all now off. Crew is patching tye holes.
5:00pm- crews headed offsite for the day.