Thursday, February 20, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:20am- No pipe will be laid today. Crew will move more materials to the bottom and then work on the roadway. 

8:05am- Iowa Trenchless is onsite at RR-04 bore pit. Gravel will be placed and light plant situated for after hours work. 

3:30pm- rails are now setting in place. 

Boring machine and augers are the next things to be moved down to the pit. 



4:20pm- Access road 3 has improved greatly today. Gas truck is supposed ti try and come in tomorrow and blasting should occur. 