7:00am- Crews are back working to finish out rock and continue with work on the forcemain.
9:30-12:30pm- Progress meeting day.
1:15pm- cleaning out bottom of hole is now underway.
2:15pm- hand work begins as the crew shovels debris into bucket.
2:50pm- after more cleaning, hole is now ready for concrete.
3:50pm- FM piping is now ready for concrete.
Concrete is also now onsite and is being placed in hole as “mud pad” begins to form.
4:30pm- grade is shot on concrete as is graded out.
4:50pm- pour is complete as water over takes it.
5:55pm- FM anchor and thrust block.