Two crews onsite this morning. They will get pumps set and begin the task of dewatering the hole.
Crane is also onsite now.
11:55am- crew is laying out ductile pipe for alignment to ensure that piers clear flanges.
12:35pm- rock breaking for gravity line connection still progressing.
4:45pm- pipe crew has laid out a portion of pipe now where it exits the ground. Gravel bedding will ensue tomorrow.
Rock breaking should wrap up midday tomorrow.